UK Government’s ambitions for removing unsafe cladding

As at the end of October 2024, there are 4,834 residential buildings 11 metres and over in height identified with unsafe cladding whose remediation progression is being reported on in this release, an increase of 13 since the end of September 2024.

Since the department first began reporting on all five remediation programmes in October 2023, 1,037 more buildings with unsafe cladding are being reported on in this release.

Overall, 2,419 buildings (50%) have either started or completed remediation works. Of these, 1,436 buildings (30%) have completed remediation works.

Figure 1: Of the 4,834 buildings identified with unsafe cladding, 2,419 (50%) have started or completed remediation works, of which 1,436 (30%) have completed remediation works. This includes remediation progress on high rise (18m+) and mid-rise (11-18m) buildings in height.

Note: From October 2023 onwards combined remediation progress is shown across the BSF, ACM programme, Cladding Safety Scheme, developer remediation contract and as reported by registered providers of social housing. The total number of buildings does not sum to the total number of buildings reported in each respective section of the data release due to crossover between schemes.

The majority of the increase in completions shown between October and November 2023 is due to a change in methodology when assigning remediation statuses for buildings that crossover between multiple schemes.

The increase in the number of reported completions between May and June 2024 is largely due to a change in methodology in reporting social housing sector remediation, which from June 2024 includes social housing buildings that had completed remediation independently of government funding and monitoring schemes before March 2024.

ACM remediation – monthly update (as at end October 2024) since previous publication

As at 31 October 2024 of the 514 high-rise (18 metres and over in height) residential and publicly owned buildings with ACM cladding systems, unlikely to meet Building Regulations, 490 (95%) have either started or completed remediation works, no change since the end of September.

Of these, 444 buildings (86%) have completed ACM remediation, including those awaiting building control sign-off, an increase of one since the end of September.

There are 24 buildings yet to start ACM remediation (5% of all buildings), an increase of 1 since the end of September. One building is vacant so does not pose a risk to resident safety, 18 occupied buildings have forecast start dates, two further buildings have had local authority enforcement action taken against them, and the remaining three buildings have come into scope in recent months.

Building Safety Fund (BSF) – monthly update (as at end October 2024) since previous publication

As at 31 October 2024, of the 810 high-rise (18 metres and over in height) residential buildings proceeding with an application for funding through the Building Safety Fund, 166 buildings (20%) have started remediation works and 352 buildings (43%) have completed remediation on unsafe non-ACM cladding, including those awaiting building control sign-off.

Overall, 518 high-rise buildings (64%) in the BSF have either started or completed remediation works on non-ACM cladding, an increase of 1 since the end of September. Of these, 352 buildings (43% of buildings) have completed remediation works, an increase of 11 since the end of September.

Cladding Safety Scheme (CSS) – monthly update (as at end October 2024) since previous publication

As at 31 October 2024, 460 buildings 11 metres and over in height have been assessed as eligible for the Cladding Safety Scheme (including 109 buildings that have transferred from the BSF), an increase of 28 since the end of September. All have either signed grant funding agreements or are in the process of doing so and are actively procuring works in the market. Of these, 31 buildings (7%) have either started or completed remediation works, an increase of 9 since the end of September. Of these, 14 buildings (3%) have completed remediation works, including those awaiting building control sign-off, an increase of 14 since the end of September.

The CSS continues to investigate and pull in potentially eligible buildings. There are a further 1,716 buildings 11 metres and over in height in the pre-eligible stages of the Cladding Safety Scheme, which launched fully in July 2023. Of these, 365 buildings are progressing through eligibility checks, and 1,351 buildings are in the pre-application stage.

Developer remediation – data received from developers as at 31 July 2024, data received from other programmes relating to developer-led remediation is as at 31 October 2024

As at 31 October 2024, 1,629 buildings 11 metres and over in height have been identified as having life-critical fire safety defects (including cladding and non-cladding defects) which developers have committed to remediate or pay to remediate (where the cladding remediation works are being carried out in a government funded remediation programme), no change since reported in the September data release.

Of these, developers reported that 772 (47%) have either started or completed remediation works, an increase of 3 since reported in the August data release. Of these, 413 (25% of buildings) are reported to have completed remediation works, no change since reported in the September data release.

When excluding buildings reported with only non-cladding defects, there are 1,452 buildings which developers have reported as having unsafe cladding, of which 718 (49%) are reported to have started or completed remediation, including 384 (26% of buildings) which are reported to have completed remediation.

Social housing sector – data received from Registered Providers of social housing as at 30 June 2024, data received from other programmes relating to social housing sector remediation is as at 31 October 2024

As at 31 October 2024, 2,539 social buildings 11 metres and over in height have been identified as having life-critical fire-safety cladding defects. These have been identified using survey data submitted by Registered Providers of social housing and data on buildings the department is monitoring under other government programmes (ACM programme, BSF, CSS and Developer Remediation contract).

Of these, 1,296 (51%) have started or completed remediation works, an increase of one since reported in the September data release. Of these, 704 (28% of buildings) have completed remediation, no change since reported in the September data release.

Enforcement – monthly update (as at 28 October 2024) since previous publication

As at 28 October 2024, local authority enforcement action has been, or is being, taken under the Housing Act 2004 against 483 buildings over 11m with unsafe cladding, an increase of 39 since the end of September.

See the full report here: www.gov.uk/

EAN Breaking News

Breaking News from the team at Estate Agent Networking. Have a new story to share with us? Then please get in contact today! When and where we can we will refer to third party websites with a 'live link back' where news was released first.

You May Also Enjoy

Breaking News

Record number of contacts for The Property Ombudsman

• 73,035 consumers contacted The Property Ombudsman in 2024 • 19,495 property businesses registered • £1.49 million awarded to consumers • 7,823 enquiries were related to tenant issues • 4,980 cases resolved by early resolution and formal investigation • 71% of cases resolved by formal investigation were found in favour of the consumer • 2,107…
Read More
Home and Living

Exercise Equipment Movers Services Los Angeles: 8 Excellent Ways for Easy Home Gym Relocation

The city of Los Angeles is a very vibrant city and one that presents challenges that are quite different from most other cities of the country. Los Angeles is known for having a diverse and vibrant culture which can be experienced both in small neighborhoods as well as in the city’s core. Los Angeles, a…
Read More
Estate Agent Talk

How to Choose an Air Conditioning Installation Engineer

With rising temperatures becoming more common in the UK, many homeowners are considering installing air conditioning systems to maintain comfortable indoor environments. However, selecting the right professional to handle your air conditioning installation is crucial for ensuring safety, efficiency, and compliance with regulations. This comprehensive guide will help you navigate the process of choosing a…
Read More
Breaking News

Over Half of UK Property Investors Plan to Expand Portfolios in 2025

  Portfolio Growth: 54% of investors intend to increase the size of their portfolios, with 73% aiming to diversify geographically and 75% sectorally, reflecting a strategic approach to growth. London Leads Again: Cited by 46% of respondents, London has regained its crown as the most attractive region, followed by the East of England at 42%.…
Read More
Home and Living

Why Walk-In Baths Can Enhance the Value of Your Home and Property

Walk-in baths are becoming an increasingly popular feature in modern homes, and for good reason. With an ageing population, a greater emphasis on accessible design, and a desire for luxury upgrades, walk-in baths offer both practical and aesthetic advantages. Beyond their health and convenience benefits, they can also significantly enhance your property’s value. Increased Accessibility…
Read More
Rightmove logo
Breaking News

Prices reach new record despite more subdued late Spring market

New seller asking prices rise by 0.6% (+£2,335) this month to a new record of £379,517. However, this month’s seasonal price increase is the lowest at this time of year since 2016, as the decade-high number of homes for sale limits price growth The traditionally strong late Spring market is more subdued following a busy…
Read More